- : 0086-21-61182423
- : 0086-21-61182425
- : [email protected]
- : Room 301,Unit 6,lane 2500,xiupu Road,Kangqiao Industrial Area,Pudong New District,Shanghai
- Improper welding of X80 pipeline may cause cracks
- Brief introduction of API X52 pipeline steel
- The difference between PSL1 and PSL2
- Harm of inclusions in X70 pipeline steel
- API 5L pipeline pipe
- X52 steel plate surface quality standards that need to be met
- The basic production process of API 5L X60 pipeline steel
- The key to Q460D steel welding process
- What does the heat treatment of Q690 Steel include?
- Reasons for choosing Q690D steel
The key to Q460D steel welding process
According to the properties of Q460D steel, the author summarizes the following key points of the welding process:
1.Preheating work. The structural parts of the hydraulic support are generally relatively thick and have high strength. In order to allow them to be heated locally, they should be preheated before welding Q460D steel. The required temperature should not be lower than 200 °C. After preheating, the Q460D steel should be welded in time, and the temperature should be around 100°C at this time.
2.Welding sequence. The first thing to weld is the vertical seam, then the beam, and finally the longitudinal seam. When welding Q460D steel, the weld seam larger than one meter should adopt the symmetrical back welding method.
3.The requirements and specifications of weld size. When welding Q460D steel, you must follow the requirements of the design drawings, and ensure that the weld width of Q460D steel is uniform and beautiful.
4.Post-weld heat treatment. Generally, the method of internal stress heat treatment is adopted to ensure the microstructure of Q460D high-strength steel and the strength of the welding seam. After welding of Q460D steel, heat preservation for 3-4 hours will help the size and stability of Q460D steel and improve the safety of Q460D steel work.
5.Inspection after welding. After the welding is completed, each weldment of Q460D steel should be inspected. If any products after welding are found to be defective, they must be dealt with immediately. Missed welding and unqualified welds are not allowed.
The above are some key points about the welding process of Q460D steel, welcome to consult and supplement.